Upstairs view of the finished floor, sanded and varnished. There are three coats of varnish on the hemlock floor. You can't quite slide on it with your socks (which is probably a good thing), but it is a nice finish.
Francois did a nice job, filling in the knots and some of the gaps that opened in the joints (it's what hemlock does).
Sunday, October 30, 2011
Finished railings and floors
The flooring detail shows how the lower grade wood actually works better in the farmhouse. The higher grade hardwood would have made it look like a concert hall or museum.
Wood flooring isn't the ideal covering for a hydronic slab. It does not conduct heat very well, and it requires a high-grade OSB subfloor to keep it stable with the expansion and contraction as well as the high humidity associated with a hydroninc slab. When Francois (the current tenant of the house) is not supplementing with wood, he needs to keep the temperature of the slab at 79 or 80 degrees F to keep things comfortable, about 5 degrees F higher than the recommended temperature for a "naked" floor.
One last finishing touch to go: the floorboards. We've got some hardwood at the sawyer that we'll use for this. It will probably be ash like the staircase.
Floors ... at last!
We finally had the floors installed downstairs and they look great. We had them installed on house II, but decided at the last minute to have part of the hardwood installed on house I.
We chose 2 1/4'' yellow birch in horizon grade (that's actually 3rd grade) from BSL (hardwood floor company from the Gaspe). This grade has knots in it, but that's okay because because the timbers also have knots in them, and the multihued daeker planks bring out the hues in the knots of all the other wood finishing we have.
Yellow birch (as the name implies) has a nice yellowish hue that matches the Hermlock timbers. It's also cheaper than the other hardwood species.
The only thing left to do now is the bedroom whcih will be done with black cherry from our own woods.
We chose 2 1/4'' yellow birch in horizon grade (that's actually 3rd grade) from BSL (hardwood floor company from the Gaspe). This grade has knots in it, but that's okay because because the timbers also have knots in them, and the multihued daeker planks bring out the hues in the knots of all the other wood finishing we have.
The only thing left to do now is the bedroom whcih will be done with black cherry from our own woods.
Saturday, January 29, 2011
Staircase II: Half done
If you look carefully, you'll notice checks (cracks) in the posts and the beams. This is what hemlock does as it dries. It actually tightens and strengthens the frame. The staircase, though, should not do this.
Staircase and Balusters
The balusters were installed around Christmas and the staircase should be ready next week. They too are made of the ash we sawed ourselves. It's hard to get a picture with all of the railings in it; it's a small house. Here you see the finished ash balusters near the top of the staircase.
The staircase is about half done.Lisa did a nice job painting the drywall at the side of the staircase. You can see the false stringers in the upper components of the stairs. The treads are still not installed and will fit on top of the structural stairs.
The staircase is about half done.Lisa did a nice job painting the drywall at the side of the staircase. You can see the false stringers in the upper components of the stairs. The treads are still not installed and will fit on top of the structural stairs.
Washer/Dryer
We bought our Kenmore washer/dryer in St. Jean during Sears days. They are now installed and doing our wash. No more trips to the laundromat. They are here temporarily until we finish Project II. This is the view from the bedroom. If you keep all the doors open, you'll be able to get undressed and do an underarm softball pitch to load the washer; everything on one floor!
The well tank is on the top right and keeps the water supply pressurized. The lighting fixture on the top of the image lights the hallway between the living area and the bathroom. Eventually, there will be a door to cover the utility room.
The well tank is on the top right and keeps the water supply pressurized. The lighting fixture on the top of the image lights the hallway between the living area and the bathroom. Eventually, there will be a door to cover the utility room.
Kitchen
The kitchen cabinets are installed, awaiting their hardwood doors. Again, we've put our stock of ash planks in Willy's capable hands to build the cabinet doors. The light fixtures are installed in the roof, and you can see the kitchen drawers at the bottom right.